|
IMN
CONFERENCE:
More
Developers Adding Power Plants
Calif. crisis, utilities' demands for large deposits driving trend
NEW YORK, Feb. 13, 2001 -- Ask OptimalPATH President Jack
Pressman why his company is investing in power generation equipment
for its carrier hotels, and the answer is simple.
"Our
motivation was because we had no other choice," said Pressman.
"The cost or delay can become such that it would prohibitively
cramp the project."
OptimalPATH is based in Chicago, where the electric company, Commonwealth
Edison, recently imposed a requirement that data center operators
put up large deposits - in some cases as much as $10 million and
more - to gain service for a facility. Florida Power & Light
has also begun seeking deposits from carrier hotel operators.
As a result, OptimalPATH is among a growing number of carrier
hotel and data center developers who are building in-house solutions
as a way to ensure a supply of affordable electric power.
"The
issue of dealing with utilities is absolutely critical,"
said Pressman. "As you get up to 150, 175 and 200 watts per
square foot, the costs to power that building can become prohibitive.
For some buildings, it just won't work.
"Our
approach is to come in asking for 40 to 50 percent less (power
from the local utility) and then build our own natural gas generators
facility, which almost pays for itself," Pressman told a
panel at this week's IMN Forum on Financing and Developing Carrier
Hotels and Data Centers. "Natural gas is, in many areas,
much more available than electric power."
The power
crisis in California has focused attention on the availability
of power, and heightened anxiety about similar problems developing
in other markets with high concentrations of power-hungry technology
businesses.
"There's
some anecdotal evidence we'll see brownouts this summer in New
York city,and perhaps some capacity issues in Northern Virginia,"
said Lewis Shadle, Senior Vice President of Business Development
for US Dataports. "This is an extremely serious issue. We
build dedicated cogeneration facilities on each of our campuses,
which provides considerable cost savings."
Operators
in markets where supply is plentiful must contend with the cost
issue, as a growing number of utilities seek large deposits as
a prerequisite to providing service. Utilities say the demands
are justified by data centers' requests for huge amounts of capacity,
ranging from 100 watts per square foot up to 200 watts.
"There's
no question that the power demands per square foot are increasing
steadily," said Brian Friedman, President of ABR Infocom.
That
demand is driven in part by the trend toward smaller server appliances
that allow colocation providers to maximize their per-square-foot
return on investment. With data center buildouts running between
$200 and $400 per square foot, that extra income can be a big
boost to margins.
But a
higher density of equipment also requires more power to run the
equipment and cool the rack space.
In most
cases, tenant power usage never actually rises to the 100 to 200
watt range, but customers want to know that the juice is there
if they need it.
"Over
the past six months we've been monitoring our power usage, and
we've not seen demand of more than 50 watts per square foot,"
said Tom Jones, President of Infomart, a Dallas-based developer
of carrier hotels. "But we'll provide 100 watts per square
foot in our facility. So the first thing we do is make friends
with the power company."
The power
issue also looms large for developers targeting smaller markets,
like Convergency Centers LLC of Grand Rapids, Mich. Company President
Peter Berns says bring-your-own power is a crucial cost-management
tool.
"We build
our own power plants, bringing in our own mini-turbines,"
said Berns. "It allows us to answer questions that have become
barriers to entry in many second-tier markets."
Adding
a power generation facility to a site also adds a wrinkle to the
company's relationship with local residents and officials, according
to Pressman.
"If
you walk into a neighborhood and say you're building a utility,
you can easily become hated," he said. "If you say you're
developing a high-tech center that's fully contained, you're able
to mask it a little and have a different process, perhaps."
OptimalPATH's
strategy has also altered its relationship with the power company.
"
We've actually been approached by Commonwealth Edison about them
buying power from us during peak loads," he said. "We're
looking very seriously at selling excess capacity back to the
utility."
What's
your opinion?
Discuss the issue in our online
forum
on power and data centers.
|